Unlocking Indonesia’s Floating Solar Potential: A PPP Regulatory Review
DOI:
https://doi.org/10.35166/jipm.v8i1.97Keywords:
Floating Solar Power Plant, Dams, Procurement, Regulation, PPPAbstract
Indonesia possesses significant potential for the development of Floating Solar Power Plant, or Floating Photovoltaic (FPV) systems, with an estimated capacity of 14,701.71 MWp. Nevertheless, the actual utilization of FPV remains very low. The Ministry of Public Works (MPW) seeks to optimize the use of multipurpose dams as FPV sources through the Public-Private Partnership (PPP) scheme. According to the data released by the Directorate of Dams and Lakes, Directorate General of Water Resources, 257 out of 259 dams nationwide are considered suitable for FPV development. Despite this potential, the implementation of PPP schemes for FPV projects has encountered stagnation. The preliminary evaluations reveal regulatory misalignment between MPW and PT PLN (Persero), which has resulted in a two-stage procurement process that is inefficient and legally ambiguous. These inefficiencies have led to adverse impacts on the government, private sector entities, and society. This study employs a qualitative approach with a Normative Legal Review Gap Analysis framework. The findings highlight the need for regulatory harmonization among MPW, the Ministry of Energy and Mineral Resources, and PT PLN (Persero). Such harmonization would facilitate the establishment of joint Contracting Agencies, a single-stage procurement process, and greater tariff certainty. The study offers policy recommendations that serve as a reference for cross-sectoral regulatory integration and enhance institutional coordination in the development of FPV infrastructure on MPW dams, thereby contributing to Indonesia’s Net Zero Emissions target by 2060.
References
APMG. (2016). PPP certification guide (Vol. Chapter 3). https://ppp-certification.com/pppguide/download
Atmo, G. U., Duffield, C., Zhang, L., & Wilson, D. I. (2017). Comparative performance of PPPs and traditional procurement projects in Indonesia. International Journal of Public Sector Management, 30(2), 118–136. https://doi.org/10.1108/IJPSM-02-2016-0047
Awuku, S. A., Bennadji, A., Muhammad-Sukki, F., & Sellami, N. (2022). Public-private partnership in Ghana’s solar energy industry: The history, current state, challenges, prospects, and theoretical perspective. Energy Nexus, 6, 100058. https://doi.org/10.1016/j.nexus.2022.100058
Decree of the Minister of Energy and Mineral Resources of the Republic of Indonesia Number 85 of 2025 on the National Electricity General Plan. (2025). https://gatrik.esdm.go.id/assets/uploads/download_index/files/28dd4-rukn.pdf
Gaol, D. K. L., Damayanti, R. A., & Kusumawati, A. (2023). Critical success factor (CSF) of implementing PPP road sector in Indonesia. Jurnal Perencanaan Pembangunan (The Indonesian Journal of Development Planning), 7(2), 209–230. https://doi.org/10.36574/jpp.v7i2.507
Hidayat, A., Ramdani, S., & Romadhoni, S. (2022). Pembangunan pembangkit listrik tenaga surya di Waduk Cirata, Kabupaten Purwakarta. Jurnal Inovasi Penelitian, 3(6), 6701–6706. https://doi.org/10.47492/jip.v3i6.2132
Iqbal, D. (2023, November 11). Berharap energi bersih terbesar di Asia Tenggara dari PLTS Cirata. Mongabay Indonesia. https://mongabay.co.id/2023/11/11/berharap-energi-bersih-terbesar-di-asia-tenggara-dari-plts-cirata/
Kartikasari, M. D., & Retnaningsih, S. (2024). Kajian mengenai skema KPBU melalui perjanjian KPBU IKN. Ranah Research: Journal of Multidisciplinary Research and Development, 6(4), 933–941. https://doi.org/10.38035/rrj.v6i4.899
Khaderi, S. S., Shukor, A. S. A., Bakri, A. S., & Mahbub, R. (2019). Public infrastructure project tendering through public private partnerships (PPP): A literature review. MATEC Web of Conferences, 266, 01015. https://doi.org/10.1051/matecconf/201926601015
Kurdi, & Syafitri, C. Z. (2024). Prinsip ESG dalam regulasi hukum KPBU: Upaya peningkatan efektivitas pembangunan infrastruktur di Indonesia. Diversi Jurnal Hukum, 10(2), 358–389. https://doi.org/10.32503/diversi.v10i2.5926
Marupa, I., Moe, I., Mardjono, A., & Malindo, D. (2022). PLTS terapung: Review pembangunan dan simulasi numerik untuk rekomendasi penempatan panel surya di Waduk Cirata. Jurnal Teknik Pengairan, 13(1), 48–62. https://doi.org/10.21776/ub.pengairan.2022.013.01.05
Maulana, M. R. (2021). Pemahaman dan pembelajaran tahap perencanaan dan penyiapan pembangunan infrastruktur di indonesia melalui skema kerja sama pemerintah dan badan usaha (KPBU) dalam penyediaan infrastruktur. JISIP: Jurnal Ilmu Sosial dan Pendidikan, 5(1), 86–107. https://doi.org/10.36312/jisip.v5i1.1646
Ministry of Energy and Mineral Resources. (2021, October 8). This is the government’s principle and roadmap to achieve net zero emission. https://www.esdm.go.id/id/media-center/arsip-berita/ini-prinsip-dan-peta-jalan-pemerintah-capai-net-zero-emission
Presidential Regulation of the Republic of Indonesia Number 38 of 2015 on Public-Private Partnership in the Provision of Infrastructure. (2015). https://peraturan.bpk.go.id/Details/41764/perpres-no-38-tahun-2015
Owojori, O. M., & Erasmus, L. J. (2025). Public-private partnerships as catalysts for green infrastructure: A three-pronged analysis of economic, environmental, and institutional factors. Frontiers in Sustainable Cities, 7, 1591278. https://doi.org/10.3389/frsc.2025.1591278
Pujianto, P., Aripriantoni, A., Sakey, P. A., & Waskito, W. (2024). Kinerja sistem array 13 PLTS terapung 145 Mw Ac Cirata dengan simulasi Pvsyst 7.4. Indonesian Journal of Energy: Mineral, 4(2), 57–66. https://doi.org/10.53026/ijoem.v4i2.2
Rahardjo, S. A., & Farudin, M. (2025). Evolusi normatif peran penanggung jawab proyek kerjasama (PJPK) dalam skema KPBU: Rekonstruksi hukum dalam tata kelola penyelenggaraan infrastruktur berkelanjutan di Indonesia. Mandub, 3(1), 144–160. https://doi.org/10.59059/mandub.v3i1.2171
Regulation of the Minister of National Development Planning/Head of the National Development Planning Agency Number 7 of 2023 on the Implementation of Cooperation between Government and Business Entities in the Provision of Infrastructure. (2023). https://peraturan.bpk.go.id/Details/271431/permen-ppnkepala-bappenas-no-7-tahun-2023
Regulation of the Minister of Public Works and Housing Number 7 of 2023 on the Second Amendment to the Regulation of the Minister of Public Works and Housing Number 27/PRT/M/2015 concerning Dams. (2023). https://peraturan.bpk.go.id/Details/257268/permen-pupr-no-7-tahun-2023
Regulation of the Public Procurement Policy Agency of the Republic of Indonesia Number 1 of 2025 on Procurement Procedures for Public-Private Partnership in Infrastructure Provision. (2025). https://peraturan.bpk.go.id/Details/314289/peraturan-lkpp-no-1-tahun-2025
Rinaldi, A., & Mulyono, J. (2021). Peluang pembangkit listrik tenaga surya (PLTS) pada genangan waduk. OSF Preprints. https://doi.org/10.17605/OSF.IO/DTBVQ
Shidqi, F., & Firmansyah, A. (2024). Bagaimana peran aparat pengawasan intern pemerintah dalam pengawasan akuntabilitas proyek kerja sama pemerintah dan badan usaha? Jurnalku, 4(1), 50–67. https://doi.org/10.54957/jurnalku.v4i1.722
Wibowo, A., & Puspita, C. (2024). The role of government support and guarantees in attracting financing for infrastructure public-private partnerships in Indonesia. Journal of Construction and Project Management, 14(2), 88–102. https://doi.org/10.15294/jpcl.v6i1.35558
World Bank. (2021). PPP reference guide version 31. World Bank Group.
Zainuddin, Z., & Hasanah, H. (2025). Implications of implementing cooperation with KPBU scheme at Hang Nadim International Airport-Batam. International Journal of Economics, Management, and Accounting, 2(10), 805–816. https://doi.org/10.47353/ijema.v2i10.245
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Muchlis Ahmad Tri Setiawan, Ahmad Sofwan, Dahwin Ferry Harahap

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
License and Copyright Agreement
In submitting the manuscript to the journal, the authors certify that:
- They are authorized by their co-authors to enter into these arrangements.
- The work described has not been formally published before, except in the form of an abstract or as part of a published lecture, review, thesis, or overlay journal.
- That it is not under consideration for publication elsewhere,
- That its publication has been approved by all the author(s) and by the responsible authorities – tacitly or explicitly – of the institutes where the work has been carried out.
- They secure the right to reproduce any material that has already been published or copyrighted elsewhere.
- They agree to the following license and copyright agreement.
Copyright
Authors who publish with Journal of Infrastructure Policy and Management (JIPM) agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License (CC BY-SA 4.0) that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgment of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.